ENERGY INDUSTRY
Construction of the HV/MV Primary Substation named “Castelgiorgio”
Client: E-distribuzione S.p.A.
- Client: E-distribuzione S.p.A.
- Location: Contrada Citerno Comune di Castelgiorgio (TR)
- Occupied area: 10.000 mq
- Collaboration: Boffetti S.p.A.
Project description
The project involved the construction and commissioning of a primary substation equipped with a HV section, featuring two 25 MVA HV/MV power transformers, 132/20 kV, located outdoors, and a MV section built with prefabricated equipment featuring 24 kV metal enclosures, single-story, AIS 24 kV container-type (CAD 2), inside which all protection, control, management, and remote control devices are installed
10.000 mq
Occupied area
25 MVA da 132/20KV
AT/MT power transformers