ENERGY INDUSTRY

Construction of the HV/MV Primary Substation named “Castelgiorgio”

Client: E-distribuzione S.p.A.

  • Client: E-distribuzione S.p.A.
  • Location: Contrada Citerno Comune di Castelgiorgio (TR)
  • Occupied area: 10.000 mq
  • Collaboration: Boffetti S.p.A.

Project description

The project involved the construction and commissioning of a primary substation equipped with a HV section, featuring two 25 MVA HV/MV power transformers, 132/20 kV, located outdoors, and a MV section built with prefabricated equipment featuring 24 kV metal enclosures, single-story, AIS 24 kV container-type (CAD 2), inside which all protection, control, management, and remote control devices are installed

10.000 mq

Occupied area

25 MVA da 132/20KV

AT/MT power transformers

Cabina Castelgiorgio panoramica