ENERGY INDUSTRY

Construction of the HV/MV Primary Substation named “San Vittore”

Client: E-Distribuzione S.p.A.

  • Cient: E-Distribuzione S.p.A
  • Location: Municipality of San Vittore del Lazio (FR)
  • Occupied area: approximately 9.480 mq
  • Collaboration: Boffetti S.p.A.

Project description

The project involved the construction and commissioning of a new main substation designed to enhance the capacity and reliability of the electricity distribution network within the municipal area and neighbouring areas.

The Primary Substation comprises a high-voltage (HV) section, two 40 MVA ONAN 150/20 kV HV/MV power transformers installed outdoors, and a medium-voltage (MV) section comprising GSCM690 switchgear. The protection, management, supervision and remote control equipment is housed within a dedicated building, in accordance with the latest technical and functional standards, in order to ensure high levels of safety, service continuity and operational efficiency.

approximately 9.480 mq

Occupied area

40 MVA ONAN 150/20 kV

2 HV/MV power transformers